[edit] Introduction
For a number of years, local highways authorities have been encouraged to develop Highways Infrastructure Asset Management Plans (HIAMPs), and the benefits of such an approach are widely acknowledged. However, changes to funding arrangements mean that authorities now have to demonstrate they not only have a HIAMP in place, but that an asset management approach is in operation and delivering benefits.
[edit] Hounslow's approach
Following a rigorous procurement process to secure funding and grant, the London Borough of Hounslow's highways pathfinder Private Finance Initiative (PFI) contract commenced on 1 January 2013. The project includes the upgrade of 259 miles of carriageway, 458 miles of footway, street lights, signs, street furniture, trees, structures, drainage and street cleansing.
The whole project was founded on highways asset management principals, which was instrumental in securing government approval.
The main features of the PFI model are:
- Financing comes from capital borrowing, supported by the government, and is released to the PFI contractor in monthly unitary charge payments, conditional on the contractor meeting the required performance standards.
- Contractual performance targets cover both operational aspects and infrastructure condition. This includes a requirement to improve highway infrastructure assets to a specified ‘steady state’ condition during the first five years of the contract and to maintain that condition for the remainder of the 25 year contract.
While it is unlikely that there will be any new highways maintenance PFI projects over the coming years, the current plan has been running for three years. This presents an opportunity to assess whether the projected asset management-related benefits are being realised, and to consider lessons learned to date.
[edit] Benefits of the Highways PFI model
The highways PFI model has a number of advantages over the conventional local authority funding model:
- Certainty of funding over 25 years.
- Opportunity for innovation.
- Economies of scale.
- Contractual service level standards.
- Commercial incentives to minimise whole life cost.
As with any HIAMP implementation there is a need for high-quality data and supporting models to ensure that contractual performance measures can be calculated, reported, audited and achieved. There is also a need to certify that the contractor is able to plan future interventions to reduce cost over the life of the project, and a need to minimise the risk of performance failures.
Ringway and Jean Lefebvre have developed their own sophisticated asset optioneering model (AOM), which can calculate whole life costs of various road construction and rehabilitation options over the network. This helps minimise costs, carbon emissions and energy consumption, while maximising performance, durability and recycling of construction waste.
[edit] Progress and achievements to date
As of July 2015 Hounslow's PFI contract has delivered the following:
- 571 carriageway schemes and 435 footway schemes.
- Around 14,000 new street lights resulting in 40% energy savings.
- 68.8% improvement in overall road and footway condition – ahead of the contract improvement profile.
- All signs and road markings replaced with long-life solutions.
- Completed upgrade of two out of the five bridges needing improvement.
- Completion of five Special Engineering Designation Schemes.
- Reduction in the level of defect reports and accident claims.
- Improved street cleansing performance and Local Environmental Quality survey scores.
[edit] Lessons learned and transferrable features
While many local authorities faced with implementing a HIAMP regime may not have the luxury of the levels of funding and long-term consistency that highways maintenance PFIs enjoy, there are a number of lessons that can be applied from projects such Hounslow's:
- It is important to be explicit about the level of performance that can be expected and afforded, with all parties signing up to measures. There should be clear, published criteria on the standards.
- There are considerable benefits to taking a long-term, technical and commercial view.
- A capital injection to build life into the network represents the lowest whole life cost solution, and can be justified by a clear business case.
- The advantages of predictability of longer-term funding, so that if the best value solution is to delay treatment for a number of years, funding will still be available, allow decisions to be made on maintenance options based on optimal timing and minimum lifecycle cost rather than availability of funding.
This article originally appeared as Highways Asset Management in Practice – Hounslow Highways PFI, published by the Institution of Civil Engineers on 13 October 2015. It was written by Satbir Gill, Network Manager, Hounslow Highways.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
- Civil engineering insights on the UK’s first Road Investment Strategy.
- Crossrail 2.
- Digital Connectivity Infrastructure Accelerator DCIA.
- Government construction and infrastructure pipelines.
- Growth and Infrastructure Act.
- Infrastructure.
- Infrastructure UK (IUK).
- Institution of Civil Engineers.
- Masterplanning.
- National Infrastructure Pipeline.
- National Infrastructure Plan.
- Types of road and street.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February